Mechanical Insulation Appraisal · Preliminary Report

Anheuser-Busch Brewery - St Louis MO - Bldg 40

Engineered findings from a NAIMA 3E Plus walk-down assessment. 6 items inventoried across 2 systems · estimated $2,126/yr in recoverable operating cost.

Executive Summary

Overview of identified insulation upgrade opportunities and projected annual savings. This is a Preliminary Report. Please see the 'Line Item Detail' Page for detailed information about each item assessed along with Infrared Imaging. Your EEQA representative will now solicit bids from our Qualified Contractors. Please allow 4-6 weeks for the bidding to complete. Your EEQA representative will then submit to you a Final Report upon it's completion. All completed upgrades will have a Quality Control visit to ensure the Mechanical Insulation was installed in accordance with specifications.

Estimated Annual Savings
$2,126/yr
Energy cost reduction from upgrades
Current Operating Cost
$2,405/yr
Inventoried surface annual cost
Upgraded Operating Cost
$279/yr
After insulation improvements
Cost Reduction
88.4%
Operating cost decrease
Heat Flow Reduction
327,349kBtu/yr
327.3 MMBtu/yr saved
CO₂ Reduction
21.63MT/yr
Metric tons per year
NOₓ Reduction
95.6lbs/yr
Pounds per year
Items Assessed
6items
Across 2 systems
Annual Operating Cost Comparison
Current (As-Found)
$2,405
per year
After Upgrade
$279
per year

Upgrading the insulation on the 6 identified items would result in estimated annual energy cost savings of $2,126/yr, a reduction in heat flow of 327,349 kBtu/yr, a reduction in CO₂ emissions of 21.63 MT/yr, and a reduction in NOₓ emissions of 95.6 lbs/yr. All calculations were performed using the NAIMA 3E Plus (version 5.1) computer program.

Savings Analysis

Energy cost savings by system area, ranked by annual impact.

Annual Energy Cost Savings by System
5-Year Projected Savings
5-Year Energy Savings
$10,628
Cumulative cost avoidance
5-Year Heat Flow Saved
1,636MMBtu
Cumulative thermal savings
5-Year CO₂ Avoided
108.1MT
Equivalent to ~4 cars off the road/yr
Environmental Impact

Emissions reductions achieved through insulation upgrades.

CO₂ Reduction
21.63MT/yr
Metric tons carbon dioxide
NOₓ Reduction
95.6lbs/yr
Pounds nitrogen oxides
Equivalent Cars Removed
~4/yr
Based on avg 4.6 MT CO₂/car/yr
Heat Flow Saved
327.3MMBtu/yr
Thermal energy conserved
CO₂ Reduction by System
System Breakdown

Summary of each system/equipment group.

SystemItemsCurrent $/yrUpgraded $/yrSavings $/yrHeat kBtu/yrCO₂ MT/yrNOₓ lbs/yr
Line-Item Detail

Complete per-item inventory with specifications and savings. Click the Item Description to view Thermal Images.

#DescriptionPipeQtyTemp °FInv. Ins.Upg. Ins.Inv ThkUpg ThkCurrent $/yrUpgraded $/yrSavings $/yrHeat kBtu/yrCO₂ MT/yr
Thermal Imaging

Infrared and visible-light photo pairs for each assessed equipment item.

STL 165

Pipe · Level 2 · Ref: 142923
Infrared
IR: Ref 142923 - IR
Ref 142923 - IR
Visible
VIS: Ref 142923 - VIS
Ref 142923 - VIS

STL 165

Pipe · Level 2 · Ref: 142756
Infrared
IR: Ref 142756 - IR
Ref 142756 - IR
Visible
VIS: Ref 142756 - VIS
Ref 142756 - VIS

STL 166

Valve · Level 2 · Ref: 143357
Infrared
IR: Ref 143357 - IR
Ref 143357 - IR
Visible
VIS: Ref 143357 - VIS
Ref 143357 - VIS

STL 166

Valve · Level 2 · Ref: 143220
Infrared
IR: Ref 143220 - IR
Ref 143220 - IR
Visible
VIS: Ref 143220 - VIS
Ref 143220 - VIS
Parameters & Methodology

Project-specific inputs and calculation methodology.

Project Parameters
Boiler Efficiency80%
Hours of Operation8,300 hrs/yr
Ambient Temperature75 °F
Wind Speed0 mph
Fuel TypeNatural Gas
Fuel Cost$5.33/Mcf

Calculation Engine

All calculations performed using NAIMA 3E Plus (v5.1), based on ASTM C680 methodology.

Inventoried Condition

Each item assessed in as-found condition. Bare surfaces have no insulation present.

Upgraded Specification

Recommended upgrades include fiberglass, cellular foam, elastomeric, and ceramic fibre materials.

Emissions Methodology

CO₂ and NOₓ calculated using EPA fuel-specific emission factors applied to energy saved.